| Table
of Contents
Concrete
Masonry, A Proven Winner for Correctional Institutions
World
Center for Concrete Technology:
New Courses
Setting
the Groundwork for a New Facility
The
Evolution of Segmental Retaining Wall Units
Concrete
Masonry Can Take the Heat
Production
Tip: Tips
to Produce Desirable Concrete Masonry Units
Besser
Block Talk: 13-5/8"
(340 mm) and 15-5/8" (390 mm) Concrete Masonry Units
Batching
and Mixing Technology for All Concrete Industries
A
New Look for Besser.com
Concrete
Masonry Units: Construction
and Landscape
Service
Tip: Prevent
Block Cracking in the Center Web
New
Product: Automatic
Kiln Doors
Product
Enhancement: Crowned
Height Pins
|
Concrete
Masonry Can Take the Heat
Fire
Stations
Concrete masonry is
one of the most predominant building materials for construction of fire
stations, primarily because of its outstanding fire ratings. While being
a highly economical choice, the additional characteristics of
durability, energy efficiency and low maintenance make concrete masonry
units a preferred building material for fire stations.
Alpena
Combat Fire Readiness Station
Alpena,
Michigan
A 22,000 square foot
(1980 sq m) Combat Fire Readiness Station is the newest addition to the
Air National Guard Base in Alpena, Michigan. The base is a military
training facility for visiting squadrons from across the United States.
The base also offers support functions to Alpena County such as fire
fighting for aircraft and structure fires.
The Readiness Station
was constructed of approximately 15,000 concrete masonry units that were
4" (100 mm) and 8" (200 mm) high. Light red, smooth faced
units were used on the majority of the exterior, while accent stripes
were created through the use of dark red, smooth and split faced units.
The color scheme worked with the texture and block selection to achieve
the low maintenance exterior desired by the client. Another reason why
concrete masonry units were chosen for this project was because of their
aesthetic and functional qualities. The wall system and decorative
arrangement of the masonry textures and colors has influenced the design
of other structures on the base.
A unique roof-framing
design diverts snow and water runoff from the
12 apparatus bay doors and protects the doors from large work vehicles.
The entire project took one year to complete and cost approximately US
$4,300,000.

Alpena
Combat Fire Readiness Station — Alpena, Michigan
Architect:
Alexander V. Bogaerts & Associates, Gaylord, Michigan
Contractor:
DeVere Construction, Alpena, Michigan
Masonry Contractor:
Boettcher Masonry, Traverse City, Michigan
Concrete Masonry Unit Supplier:
4D, Inc., Midland, Michigan
Croswell Fire Department
Croswell,
Michigan
The Croswell Fire
Department was completed in March 1999 after nearly five months of
construction. The US $478,000 building houses fire equipment, a training
and meeting room, kitchen and fire hall.
Approximately 5000
concrete products were used to construct the 7596 square feet (684 sq m)
fire department. The project used 8" (200 mm) and 12" (300 mm)
mauve split face and 8" (200 mm) mauve single scored, smooth face
concrete products. Integrally colored masonry and single scored, smooth
face units created a large accent band around the upper portion of the
building. Building windows were highlighted with smooth face units.
The City of Croswell
chose concrete products for the fire department because of its low
maintenance costs and longevity. Split face concrete products were also
used on the nearby Department of Public Works building. Concrete masonry
is the building material of choice for future government buildings in
the neighboring industrial park.

Croswell
Fire Department — Croswell, Michigan
Architect:
Elten Engineering, Port Huron, Michigan
Contractor:
Jerry Bartow, Lexington,
Michigan
Masonry Contractor:
B&L Masonry, Yale, Michigan
Concrete Masonry Unit Supplier:
Theut Products Inc., Romeo, Michigan
Fire
Station No. 2
Morrisville,
North Carolina
Fire Station No. 2 of
Morrisville, North Carolina is a display of the unique design beauty
made available by concrete masonry construction. The exterior of the
building is constructed of 17,000 4" x 4" x 16" (100 mm x
100 mm x 400 mm) brickstone veneer in colonial creme and pecan.
Approximately 13,000 lightweight concrete masonry units in 8" (200
mm) and 12" (300 mm) were used as reinforced masonry backup.
One of the reasons
for choosing concrete masonry units for this project was because of the
beautiful aesthetics it adds to the structure. Other deciding factors
were the durability and low maintenance qualities inherent in concrete
masonry building materials. The Northampton 911 and Emergency Management
Center was influenced by this project and will be constructed with the
same type of concrete masonry units.
Fire Station No. 2
was constructed in nine months and completed in 1999. The building is
8715 square feet (784 sq m) and the entire project cost was
approximately US $1,024,000.

Fire
Station No. 2 — Morrisville, North Carolina
Architect:
Surapon Sujjavanich Architect PA, Apex, North Carolina
Contractor:
Patriot Building Co., Inc., Hillsborough, North Carolina
Masonry Contractor:
Carolton T. Whitmore Masonry Contractors, Mebane, North Carolina
Concrete Masonry Unit Supplier:
Adams Products Company, Morrisville, North Carolina
Menomonee Falls Fire Station No. 4
Menomonee
Falls, Wisconsin
Concrete masonry
units were chosen for the Menomonee Falls Fire Station No. 4 in
Menomonee Falls, Wisconsin for its beauty, durability, economy and
energy efficiency. The 8400 square foot (756 sq m) station contains
approximately 14,150 lightweight, 3,000 decorative and 760 vertically
scored concrete masonry units.
Building detail was
created by 4" (100 mm) veneer units, 16" x 16"
(400 mm x 400 mm) split face and 8" x 8" (200 mm x 200 mm)
spectra glazed units. Placing a single, vertical score in the glazed
masonry units resulted in an attractive 8" x 8" pattern. The
exterior walls are "cavity walls" with 8" back-up and 3
inches (76 mm) of rigid polystyrene insulation.
Concrete masonry
architecture was used on the bell tower to frame the main entrance of
the fire station. The dramatic use of charcoal and red provides an
eye-catching display.

Menomonee
Falls Fire Station No. 4 — Menomonee Falls, Wisconsin
Architect:
Fischer-Fischer-Theis, Inc., Waukehsa, Wisconsin
General Contractor:
A.J. Heinen, Inc., New Berlin, Wisconsin
Masonry Contractor:
Lloyd S. Hamm, Inc., Muskego, Wisconsin
Concrete Masonry Unit Supplier:
Best Block Company, Menomonee Falls, Wisconsin
The New Berlin Fire
Station No. 1 in New Berlin, Wisconsin was constructed in just 8 months
at a cost of US $700,000. The 11,900 square foot (1071 sq m) building
includes a large apparatus bay for twelve pieces of equipment, a hose
tower, a day room, a dormitory, a kitchen, two offices and other
ancillary spaces.
Concrete masonry
units were chosen for this project because of their inherent qualities:
aesthetically pleasing, durable, economical, readily available and fire-
resistant. Split face units in light tan were used on the exterior of
the building. Smooth face units created horizontal ribbons, which accent
the exterior walls. Concrete masonry units in 4" x 8" x
16" (100 mm x 200 mm x 400 mm) were used with a 4 inch (100 mm) air
space or cavity and 8"
(200 mm) block back-up.
A dramatically
designed hose tower on the front of the building lends a monastery feel
to the building. Split face concrete masonry units and glass block work
well together to add simple yet effective dimensions to the project.
The architecture of
the New Berlin Fire Station No. 1 influenced the design and construction
of the recently completed New Berlin Public Safety Building that stands
adjacent to it. Although the color on the two projects are different,
the styles are complementary.

New
Berlin Fire Station No. 1 — New Berlin, Wisconsin
Architect:
Fischer-Fischer-Theis, Inc., Waukesha, Wisconsin
General Contractor:
Siesel Construction Co., Milwaukee, Wisconsin
Masonry Contractor:
Keystone Masonry, Germantown, Wisconsin
Concrete Masonry Unit Supplier:
Waukesha Block, Waukehsa, Wisconsin
Terre
Hill Fire House
Terre Hill, Pennsylvania
A steel building with
a concrete masonry base was the first consideration for the Terre Hill
Fire House. According to Jim Eberly, chairman of the building committee,
"We decided the building would look better with block and it would
be more durable. Our goal was to have an attractive, cost-effective
building and we were happy with our decision to use concrete
masonry."
Tom Weaver,
architect, was also pleased with the aesthetics of concrete masonry. He
had worked with concrete masonry previously around his house and liked
the color and finish options available. The building was designed with
split and smooth face concrete units in chocolate brown, sandstone brown
and buff tan to add unique design elements while keeping within the same
color scheme. "I feel we created an attractive building that is
going to last a long time," stated Tom.
Approximately 4300
concrete masonry units were used to construct this US $300,000 project.
The first floor is 5008 square feet (450 sq m) and the second floor is
1900 square feet (171 sq m). The Terre Hill Fire House was completed in
1995 after eight months of construction.

Terre
Hill Fire House — Terre Hill, Pennsylvania
Architect:
Thomas L. Weaver, Ephrata, Pennsylvania
Contractor:
Weaver Construction, East Earl, Pennsylvania
Masonry Contractor:
Robert S. Weaver Masonry, New Providence, Pennsylvania
Concrete Masonry Unit Supplier:
New Holland Concrete, New Holland, Pennsylvania
|