| Loadbearing concrete
masonry is a proven system that provides structural support and attractive
walls at an economical cost. Construction methods used are based on
simple, one-story structures, with some modifications depending on the
building height and location. An added benefit is the architectural system
may be part of the structural system.
Project Planning
Coordination and planning are the keys to fast, quality construction at
an economical cost. Prior to foundation construction, meetings held
between the general contractor, mason contractor, architect, structural
engineer and masonry supplier created a valuable understanding of the
construction requirements.
These meetings insure that the project starts on time and the
transition between building trades is smooth. Before placing the
foundation, the mason contractor and foundation contractor should
coordinate vertical wall reinforcement. This will insure that dowels are
placed at the location of the block cores. If this alignment is not
accomplished, misplaced dowels may be bent at a 1:6 ratio from the
intended position to match wall reinforcement. If bending is not possible,
the block webs must be cut out.
Masonry Units
Since concrete masonry units are manufactured using automated equipment
under controlled conditions in a factory, variations between units are
minimized. Factory settings provide an opportunity to test units prior to
construction.
Concrete masonry unit strength is the major factor determining the
strength of loadbearing masonry walls. Current manufacturing methods
result in the production of concrete masonry units which are 2 - 3 times
higher than the compressive strength specified by ASTM C90. This allows
the use of different strength units for different levels of the building.
The net compressive strength of masonry, f1m,
can be determined by two methods: unit strength method and prism test
method.
Using the unit strength method, block are sampled from the construction
site and tested in a laboratory in accordance with ASTM C140. The net unit
strength is correlated on a table (Table 1) with the appropriate mortar
type to determine the f1m
of the masonry.
Table 1 Compressive strength of
masonry based on the compressive strength of concrete masonry units and
type of mortar used in construction.
|
Net
area compressive strength of concrete masonry units
psi (MPa) |
Net
area compressive strength of masonry psi1 (MPA)
f1m |
| Type
M or S mortar |
Type
N mortar |
| 1250
(8.62) |
1300
(8.96) |
1000
(6.90) |
| 1900
(13.10) |
2150
(14.82) |
1500
(10.34) |
| 2800
(19.31) |
3050
(21.03) |
2000
(13.79) |
| 3750
(25.86) |
4050
(27.92) |
2500
(17.24) |
| 4800
(33.10) |
5250
(36.20) |
3000
(20.69) |
| 1For
units of less than 4 in. (102 mm) height, 85 percent of the values
listed. |
Following the prism strength method, a two-block high prism is
constructed on site using full mortar bedding and the same mortar as used
to lay block. The prism is then tested in accordance with ASTM C1314 in a
laboratory to determine the f1m.
(Note: It is advisable to build a prism on a wooden plank and strap
another plank on top to prevent cracking the mortar joint during handling
and transit.) Normally, 28-day strengths are required, but seven-day
strengths are commonly permitted if a correlation can be shown by
historical performance.
If multiple strengths of concrete masonry units are used on the same
project, it is advisable to identify the units or cubes of units. Proper
labeling will insure that the correct strength units are used. Marking can
entail the use of molded marks, color pigmentation or spray, stamps or as
a minimum, marking individual cubes of block.
Inspection
Contract documents specify the level of inspection necessary which
depends upon the facility function and its design method. The details of
the minimum submissions and inspection are defined in Section 1.14 of the
Masonry Standards Joint Committee (MSJC) code.
Level I:
applies to nonessential buildings designed under the
empirical design method. Certificates that show the materials comply with
the specifications are the only product submissions required.
Level II:
applies to essential buildings designed under the
empirical design provisions and for nonessential buildings designed under
other design provisions. In addition to certification of materials,
verification of the net compressive strength is required prior to
construction.
Level III: applies to essential buildings designed under the design
provisions. In addition to prior verification of f1m,
the strengths should be verified every 5000 sq. ft. (464.6 m2)
during construction.
Tolerances
The masonry elements must be built to the appropriate tolerance to
insure the structural performance of the masonry structure. Section 3.3G
and section 3.4 of the MSJC specifications contain the acceptable
construction tolerances.
Mortar
The mortar type is specified by the designer. The field properties of
the mortar should be compatible with the weather and masonry product
properties. As an example, low water content and high initial absorption
or stiff mortars make vertical alignment difficult. Likewise, fluid
mortars make alignment difficult and prevent rapid unit placement and wall
construction.
Avoid mortars with higher cement contents than specified. High cement
content mortars tend to have more water which can cause the mortar to
become brittle and shrink resulting in cracks.
Since mortar is normally prepared on site, it has the largest potential
for variation. Consistency of mortar, through accurate control of
proportions, will insure a quality structure, control material costs and
possibly lower labor costs. It will also allow masons to lay block faster
and more accurately.
If available, the use of prepackaged mortar and silo mortar systems
should be prepackaged mortar and silo mortar systems should be seriously
considered to improve mortar consistency. The ability to produce mortar
quicker using newer equipment and systems creates the increased
possibility that mortar can begin its initial set. This mortar can be used
if retempered on the mortarboard. This permits using the mortar 2 - 3
hours after mixing, depending on the temperature.
Most basic structural units
are available with either a smooth or architectural face (as shown in
photo).
Grout
Grout is a cementitious mix of sand, cement and possibly fine
aggregate. It is used to fill bond beams and cores containing reinforcing
steel. Normally, only spaces containing steel are filled. The grout should
be the same strength as the concrete masonry units. Concrete should not be
used in place of grout.
There are two types of grout defined in ASTM C476. The selection of the
type of grout depends on the grout pour height and the minimum grout space
requirements. Grout should be placed within 1-½ hours of mixing.
When placed, grout should have a slump of 8" - 11" (200 mm -
280 mm) to insure complete filling of the desired voids. In contrast to
concrete, excess water is beneficial to proper grouting. The excess water
assists in complete filling and providing a good bond to the
reinforcement. The masonry units absorb the excess water causing initial
grout settlement which creates an ideal environment for curing grout. Dry
grout is subject to bridging, especially if the walls of the entire grout
cell are not smooth and continuous.
Grout may either be pumped or placed with buckets. Grout pours must be
consolidated by mechanical means or puddling. Pours more than 12"
(300 mm) must also be reconsolidated after settlement has occurred;
excessive vibration should be avoided. The top surface of a grout lift
should be kept about 1-½" (38 mm) below beams flush with the top of
the unit. If using an open bottom bond beam, it is desirable that the webs
align with the webs of the unit below and mesh, screen or any other
barrier is used to prevent grout from filling the cores.
Reinforcement
Reinforcement should be placed before grout is placed and not worked
into the grout later. This insures proper location and embedment.
Provision should be made to provide the proper length for lapping future
reinforcement in the walls above. Prior to grouting the last lift of a
wall and filling the bond beam, reinforcement should be placed to provide
a continuous connection to the floor system.
Depending on the grout type, 1/4" or 1/2" (6 mm or 13 mm)
spacing should be maintained between the reinforcement and the masonry
unit. When the masonry wall is exposed to the weather, 1-½" (38 mm)
of cover is required between the reinforcement and the exposed surface.
Section 1.14 of the MSJC code provides detailed information on placement
tolerances.
Execution
Concrete masonry units with the correct geometry should be selected. If
the project requires full mortar bedding, use units with webs that align
when laid in the specified bond. In running bond, units laid must lap the
underlying units by 1/4" - 1/2" (6 mm - 13 mm) of the unit
length. If vertical steel and grout are used, the cell containing grout
must be sealed from adjacent cells by a mortar dam or mortar on the cross
webs. Care should be taken to construct the grout cell as vertical as
possible with minimum projections into the grout core or changes in
vertical grout face.
Mortar joints must be maintained as close to 3/8" (10 mm) for both
strength and appearance. Joint reinforcement in the mortar must be lapped
as a crack control measure to insure structural integrity and performance.
If high lift grouting will be used, clean-out holes on the face of the
wall should be provided for the cores to be inspected. Cutouts can be used
for plain block, but face shells should be removed to permit inspection
and cleaning. The openings should be filled prior to grouting.
Weather
Cold:
In cold weather construction, there are two main concerns:
preventing the mortar from freezing when it is saturated and protecting
the wall during the time immediately after construction. These provisions
usually require special care for raw materials and protect the wall during
and after construction. Heating may be required. The National Concrete
Masonry Association’s TEK 3-1A provides detailed information on the
degree of protection for different conditions.
Hot:
In hot weather construction, the temperature of the mortar
should be kept below 120o F (38o
C). Smaller batches of mortar may be used to decrease the length of time
between mixing and laying units. In hot weather, it is advisable to use
cool water to prolong mortar board life. To prevent mortar from drying out
after units are laid, the wall should be protected or covered if winds are
present.
Precipitation:
Completed walls should be protected from rain until
the mortar joints and grout have been satisfactorily cured. This will
insure consistent color and appearance.
Summary
Constructing economical, high quality mid and high rise loadbearing
masonry structures is similar to constructing ordinary structures.
However, multi-story projects require additional planning and other
provisions may be made. Proven performance of concrete masonry units for
mid and high rise buildings has led to a steady increase in use.
References:
- Masonry Standards Joint Committee,
"Building Code Requirements for Masonry Structures," ACI
530/ASCE 5/TMS 402, and "Specifications for Masonry
Structures," ACI 530.1/ASCE 6/TMS 602, ACI, Detroit, Michigan;
ASCE, New York, New York; TMS, Boulder, Colorado, 1999.
- All Weather Concrete Masonry
Construction, NCMA TEK 3-1A, National Concrete Masonry Association,
Herndon, Virginia, 1995.
- "Masonry Structures Behavior and
Design," Robert G. Drysdale, Ahmad A. Hamad, Larwie R. Baker, The
Masonry Society, Boulder, Colorado, 1999.
- ASTM Standards, American Society of
Testing and Materials, Philadelphia, Pennsylvania, 1999.
|